Hafeet Rail progress in 2026 at a glance
2026 is the year Hafeet Rail moved from earthworks to track, gained its legal footing in Oman and was given its first operating date: trials, not service. Here is what changed, in order.
| Date | What happened | Source |
|---|---|---|
| 21 April 2026 | Hafeet Rail announced 40% completion | Ministry of Finance, 22 April |
| June 2026 | Track laying and installation began | Oman Observer, 6 June |
| 21 June 2026 | Oman and the UAE signed the Agreement on the Development of the Railway Link | decree.om |
| 19 July 2026 | Mwasalat presented a Sohar transport hub linked to the coming Hafeet station | Oman Observer |
| 3 September 2026 | Royal Decree 75/2026 ratified the agreement; Official Gazette 1664 on 6 September | decree.om |
| September 2026 | The transport minister set trial operations for Q4 2027 | Oman Observer, 19 September |
| 9 November 2026 | GCC ministers signed a General Agreement to integrate the national railways | Oman Observer |
| 11 November 2026 | Hafeet Rail launched Masar Hafeet to train Omanis for railway jobs | Oman Observer |
For what the line means for homes and land, read our evergreen piece on Hafeet Rail, the Muscat Metro and Oman property.
Hafeet Rail 40% complete: what the April figure covers
The railway is a joint venture of Etihad Rail, Oman Rail and Mubadala Investment Company, building 238 km from Sohar Port through Wadi Al Jizzi and Al Buraimi to Al Ain, where it joins the UAE national network. In its April announcement, carried by the Ministry of Finance, the company reported 27 million cubic metres of earthworks complete and more than 100,000 cubic metres of concrete poured. Work was under way on 80 structures, with 900 piles and 130 box culverts being built and tunnels 1 and 2 advancing through the Hajar mountains. Facilities were going up in Sohar and Al Buraimi, and the project counted 10 million working hours without a major injury.
The chief executive of Asyad Group, Abdulrahman Al Hatmi, said the pace reflected the commitment to begin "passenger and freight services as planned". No newer percentage has been published since April. When one is, it is the number to watch.
Track laying and the Oman-UAE railway agreement
In early June the project disclosed that track laying and installation had begun, the Oman Observer reported. The line includes about 2.5 km of tunnels and 60 bridges, some of them 34 metres high.
On 21 June the two governments signed the Agreement on the Development of the Railway Link. Sultan Haitham ratified it by Royal Decree 75/2026 on 3 September, with effect from that day, and it was published in Official Gazette 1664 on 6 September. Gulf News put the project at about USD 2.5 billion, with USD 1.5 billion of financing from regional and international banks. The decree gives the railway its treaty basis in Omani law, which matters for a line that will run trains and customs across a border.
Trial operations in Q4 2027: what the minister said
In September the Minister of Transport, Communications and Information Technology, Said bin Hamoud Al Maawali, said: "Trial operations for the train connecting the Sultanate of Oman and the UAE will begin in the fourth quarter of 2027", as the Oman Observer reported. It is the first operating date given for the line.
Read it carefully. Trials test the track, signalling and trains; they do not carry paying passengers or contracted freight. Commercial freight and passenger services follow, and neither has a date. The design numbers are set: passenger trains up to 200 km/h, about 100 minutes from Sohar to Abu Dhabi and 47 minutes from Sohar to Al Ain, and freight trains carrying up to 15,000 tonnes, according to Hafeet Rail.
Sohar station and the transport hub
Sohar is the line's Omani terminus and its reason for being: Hafeet Rail links Sohar Port to the UAE's ports and industrial zones. The company says the network connects more than 12 passenger stations and cities across both countries, but no station list or design for the Sohar passenger station has been published. In July the state transport operator Mwasalat asked investors and developers to join a bus and taxi hub in Sohar which "will connect the upcoming Hafeet train station with the Port of Sohar and Suhar International Airport", the Oman Observer reported. No cost or timetable was given.
The GCC railway and the 2030 target
On 9 November GCC transport ministers signed a General Agreement in Manama to link the national railways into a single interoperable network. The GCC network, 2,117 km across the six states, was put at about 56% complete, with full operation targeted for December 2030, as the Oman Observer reported. Hafeet Rail is Oman's link into it. The same week Hafeet Rail launched Masar Hafeet, a programme with Takatuf Petrofac Oman to train young Omanis as train captains, controllers and technicians, a sign the company is preparing to operate.
What the 2026 progress changes for property in Sohar and Al Batinah
Expectations have moved faster than trains. Residential land in North Al Batinah, which includes Sohar, rose 29% in the year to Q2 2026, and Muscat land 40.6%, according to the NCSI figures reported by Times of Oman. Al Buraimi, which the line crosses, rose 3.1%. Finished homes rose far less: villas 10.8% nationally.
Two things have become clearer this year. The line is real and funded, with a legal basis and a trial date. And service is still at least a year beyond the trials, with no station plan for Sohar. A buyer should price land or homes near the line on what exists now, the Batinah Expressway, the port and the industrial zone, and treat the railway as upside with a date still to be fixed.
Ownership limits apply too. Foreign buyers may own only in designated areas, mainly Integrated Tourism Complexes and the future cities; the Ministry of Housing and Urban Planning said in June 2026 that foreign ownership "has not been opened to all areas of the Sultanate". GCC citizens, including buyers from the UAE who will use the line, may own built property and land under the GCC rules.
What a buyer should do now
- Track three numbers. A completion percentage newer than April's 40%, the start of trials in Q4 2027, and the first date for passenger or freight service.
- Ask for the station plan. Until Sohar's passenger station is mapped, a "near the station" claim cannot be checked.
- Check who can own. Our guide to foreign ownership sets out the designated areas, and Gulf buyers can read our guide to buying property in Oman from the Gulf.
- Weigh the wider economy. Our guide to Oman's economy and property demand puts the railway beside the ports, tourism and the 2028 income tax.