Oman's Real Estate Regulation Law, Royal Decree 79/2025, defines the project completion certificate as the document the competent authority issues, on the request of the project's consultant, showing that the project has been completed (Article 1). Several rules run from its date:
- outside the ITCs, the developer must manage the common parts for at least two years from the certificate before handing them to the owners' association (Article 48);
- under the 2020 usufruct rules, foreigners could buy flats only in buildings no more than four years from their completion certificate (Ministerial Decision 357/2020);
- the Golden Residency's property route needs a completed ("ready-made") ITC unit with a title deed, so completion is the first step towards it.
Before you make the final payment on an off-plan home, ask the developer for a copy of the certificate and check that it covers your building and phase. Then book the snagging inspection and prepare for handover. See off-plan property in Oman and the Golden Residency.